This website stores cookies on your computer. These cookies are used to collect information about how you interact with our website and allow us to remember your browser. We use this information to improve and customize your browsing experience, for analytics and metrics about our visitors both on this website and other media, and for marketing purposes. By using this website, you accept and agree to be bound by UVic’s Terms of Use and Protection of Privacy Policy.  If you do not agree to the above, you can configure your browser’s setting to “do not track.”

Skip to main content

Petch Air Balancing and Repairs

Monday, April 27: Petch rooms 034, 035, 036, 038
Wednesday, April 29: Petch Rooms 057, 059, 068, 159, 252, 257

Facilities Management JB Sheetmetal and Rain City Technical have
restarted their air balancing efforts in your building.

As before, technicians will be shutting down fans servicing rooms in
Petch listed above, for one hour and then taking measurements for
airflow in the rooms they service after restarting the fans. There
may be a need to revisit rooms or shut off the fans again
temporarily for testing.

Please take the following precautions:
1. Please refrain from using fume hoods during this time.
2. Please store all hazardous chemicals in the appropriate acid
or flammable cabinets and wipe up any spills inside fume
hoods. Our technicians are unable to tell if a spill is just
water or something more serious.

Mon, April 27, 2026: 7:00am-8:00am Shutdown of FE-1 Fan,
7:00am – 1:00pm Room access to PCH 034, 035, 036, 038
Wed, April 29, 2026: 7:00am-8:00am Shutdown of CAF-3B System,
7:00am – 1:00pm Room access to PCH 159, 057, 059, 068, 252, 257
*PCH 159 will be prioritized to finish first

View/Download Facilities Notice: PCH Building Air Balancing and Repairs

Contact/Organizer Name: Harman Brar, Project Manager