Petch Shared Research Facilities Renovation

Rooms 026 to 031, basement of the Petch Building

Facilities Management and Aral Construction (2014) Ltd. are undertaking a project that will renovate the rooms 026 to 031 into a shared, BSL2 and BSL2+ laboratory space. Aral Construction will be installing new epoxy floors in these rooms during the last week of August.

Some off-hours noise will be produced, and the rooms will not be accessible during this week for any reason, to allow the floor time to cure.

Please reach out to me (Jen Miley) with any questions or concerns.

Date

Shift Start Time

Shift
End Time

Activity

Monday, August 28, 2023

6:00PM

2:00AM

Floor preparation (noise)

Tuesday, August 29, 2023

6:00PM

2:00AM

Floor preparation (noise)

Wednesday, August 30, 2023

10:0AM

6:00PM

Installation of epoxy floor

Thursday, August 31, 2023

8:00AM

4:00PM

Installation of epoxy floor

Friday, September 1, 2023

8:00AM

4:00PM

Installation of epoxy floor

View/ Download Facilities Notice - PCH Shared Research Facilities Reno

Contact/ Organizer Name - Jen Miley, Project Manager

Contact/ Organizer Email Address - jmiley@uvic.ca