Parking Lot Repairs in various locations – Revised Schedule

Parking Lots: 2, 6, 7, 9, 12, 15

Facilities Management and Island Asphalt will be doing asphalt repairs and re-paving in various parking lots around campus from June to August 2023.

The proposed schedule is as follows;

  • June 12th - Lot 4 - Completed
  • June 13th – Lots 1 & 2 - Completed
  • June 15th & 16th – Lot E - Completed
  • June 19th to July 3rd – Lot 7
    o     Asphalt removal completed 2023-06-20
    o     Patch paving planned for 2023-06-30
    o     Top lift overlay planned for 2023-07-03
  • June 21st to July 3rd – Lot 2 (N.W.)
    o     Asphalt removal 2023-06-21 to 23
    o     Patch paving planned for 2023-06-30
    o     Any final paving cleanup 2023-07-03
  • June 28th to 30th – Lot 12
    o     Asphalt removal June 28th to June 29th
    o     Paving June 30th
    o     Lot ready for use Monday July 3rd
  • July 4th & 5th – Lot 15
  • July 6th to 10th – Lot 2 (N.E.)
  • July 11th to 14th – Lot 2 (S.E.)
  • July 20th to 26th – Lot 2 (S.W.)
  • July 27th to Aug 4th – Lot 9
  • Aug 8th to 10th – Lot 6

June 19 - August 10, 2023

View/ Download Facilities Notice - Parking Lot Repairs-REV Date

Contact/ Organizer Name - Randy Carter, Project Manager

Contact/ Organizer Email Address - rcarter@uvic.ca