Engineering Lab Wing A140 Lab – Concrete Coring & Duct Installation

Engineering Lab Wing (ELW) Room A127 & A117

Facilities Management, AME Consulting and Aral Construction Ltd. are working on renovations in ELW 140 Fluid Mechanics and heat transfer lab. For this scope of work to be completed, work will occur in rooms A140, A127 and A117, corridor’s (as required) and mechanical penthouse.

For this project notice, the contractor needs to core a hole through a concrete wall between rooms A127 and A117. Both rooms will be hoarded as shown in the drawings attached. The coring equipment will be installed in A127. During this time period and due to the hoarding, access to A117 can only be through A107 and access to A119 can only be through A123. Hoarding will be up in both rooms for approximately 2 weeks to install ducting after the core is completed.

We apologize for any inconvenience.

March 30, 2023, All-Day – Install Hoarding

March 30, 2023, 6:00 pm-9:00 pm – Coring

March 31-April 14, 2023, intermittently all-day – Duct install and hoarding will stay up

View/ Download Facilities Notice - ELW A140 Lab-ConcreteCoring/Duct Install

Contact/ Organizer Name - Neel Chadda, Project Manager