Engineering Lab Wing (ELW) Boiler Room Renovation - REVISED

Engineering Lab Wing (ELW) boiler room

 

Facilities Management and Aral Construction are currently working on the renovation of the boiler room on the north side of the building. Concrete demolition will be this occurring as noted in days and times listed below. There will be noise coming from tools and equipment.

We apologize for any inconvenience this work may cause. Please contact the Project Manager with any concerns or questions.

Monday Night March 13, 2023 11:00 pm - 7:30 am

Tuesday Night March 14, 2023 11:00 pm - 7:30 am

Wednesday Night March 15, 2023 11:00 pm - 7:30 am

View/ Download Facilities Notice - ELW Boiler Room Reno-REVISED

Contact/ Organizer Name - Mark Arrojado, Project Manager

Contact/ Organizer Email Address - markarrojado@uvic.ca