Bob Wright Centre – B-Wing
Facilities Management is working with SRD Controls on the replacement of Direct Digital Control (DDC) system controllers that control the heating, ventilation, and air conditioning (HVAC) in the Bob Wright Centre.
The first phase of this work will be the installation of new data cabling to each lab on the second and third floor of B-Wing. This work will mostly take place in the hallways but will branch into each lab to the ventilation controller location.
There will be no impact to any systems during this phase.
Third floor labs – Monday, January 9 to Friday, January 13, 2023
Second floor labs – Monday, January 16 to Friday, January 20, 2023
7:00am to 4:00pm each day
View/ Download Facilities Notice - BWC-Update of DDC Systems
Contact/ Organizer Name - Terry Moen, Project Manager
Contact/ Organizer Email Address - tmoen@uvic.ca