Science Buildings Renovations - Site Office

Exterior Petch Building – South East, adjacent Loading Dock

On Thursday, March 30th between 7am and 9am, Kinetic Construction is scheduled to deliver security fencing for their compound for the Science Buildings Renovations project. (See attached plan for location.)

This will be followed on Friday, March 31st by the delivery of the site office and storage containers. Kinetic will maintain traffic control procedures in place throughout offloading. Access to surrounding buildings will be maintained at all times.

The compound is expected to be in place from March 30, 2017 for 15 months until the completion of the project in June 2018.

View/ Download Facilities Management Notice - Science Buildings Renovations - Site Office

Contact/Organizer name: Scott Kingham, Senior Project Manager, Secondary Contact: David Hill, Senior Project Manager