Petch Building - Roofing and Cooling Plant Installation

As part of the Science Buildings Renewals project, cooling equipment will be installed on the Petch building roof. Work will include partial re-roofing at the west end of Petch and installation of a steel platform, two large cooling plants (chillers) and a pump house. If a more detailed schedule is required, please contact the project manager.

September 9, 2017 through November 9, 2017.

  • Concrete and Steel Supports – Tuesday, September 5, 2017.
  • Roofing Work – Monday, September 25, 2017
  • Steel Platform – Tuesday, October 3, 2017
  • Chiller Units – Thursday, October 19, 2017
  • Pump House – Monday, October 30, 2017

View/ Download Facilities Management Notice - Petch Building - Roofing and Cooling Plant Installation

Contact/ Organizer name: Scott Kingham, Project Manager or David Hill, Colliers Project Manager

Contact/ Organizer email: skingham@uvic.ca or David.Hill@colliersprojectleaders.com