New Service Building / Surveying - Reduced Parking Area

Parking Area behind Saunders Workshops (sketch attached)

Perma Construction will be surveying and setting out locations of the utility line which will service the New Services Building, as of 1:00pm on Tuesday, June 06. To facilitate this work, it is requested that at that time, no UVic or private vehicle park in the hatched area indicated on the attached plan.

Once excavation commences in this area (likely as of Wed., June 07) this space will not be available for parking. Perma Construction will place steel plates across the excavated trenches, permitting vehicles and pedestrians to cross the trenches. A further Project Notice will be issued regarding the confirmed start and duration of excavation in this area.

Starting Tuesday, June 6, 2017 at 1:00pm until further notice

View/ Download Facilities Management Notice - New Service Building/Surveying-Reduced Parking Area

Contact/ Organizer name: Nazir Jessa, Consulting Project Manager

Contact/ Organizer email: njessa@uvic.ca