For the week commencing Monday September 23, Facilities Management and the Construction Managers, EDK, will be undertaking the work noted below.

Service Road
Curbs will be installed at Sinclair entrance on Monday. Additional flaggers will be in place and delivery access maintained. A separate notice will be issued confirming the dates and times of any road closures.

Masonry
Installation of brickwork to be completed at Joseph Cunliffe and commence at the SUB waste compound.

Landscape
Hydroseeding all new soft landscaped areas.

Site Fencing
Site fencing will be reduced before the end of the week.

September 23 – September 27;  7:30am to 4:00pm

View/ Download Facilities Notice - SHD Site Prep Constr Activities Sept 23

Primary Contact/ Organizer name: David Hill, Senior Project Manager
Primary Contact/ Organizer email: david.hill@colliersprojectleaders.com

Secondary Contact/ Organizer name: Scott Kingham, Project Manager
Secondary Contact/ Organizer email: skingham@uvic.ca