Student Housing and Dining (SHD): Tower Crane – Building Two

SHD Construction Site (Gate 3) and Parking Lot 5

Facilities Management and EDK are planning the delivery and installation of the tower crane for Building Two of the SHD project, with the timeline as follows:

December 9 (4pm) – Parking stalls delineated for staging (see Lot 5 map).

December 10: Multiple trailer drops to staging area.

December 11: Multiple deliveries, Tower section of crane erected.

December 12: Multiple deliveries, Boom section of crane erected.

December 14: Crane is commissioned. Demobilization from site.

Flaggers will be in place between the staging area and Gate 3, assisting pedestrians and diverting vehicle traffic as required.

Emergency access will be maintained throughout, however there will be some interruptions to normal traffic flows as wide loads are moved onto site at Gate 3.

Wednesday, December 9 – Monday, December 14, 2020

View / Download Facilities Notice - SHD Tower Crane – Bldg Two

Primary Contact/ Organizer name: David Hill, Senior Project Manager
Primary Contact/ Organizer email: david.hill@collierprojectleaders.com

Secondary Contact/ Organizer name: Gerry Underhill, Project Manager
Secondary Contact/ Organizer email: gunderhill@uvic.ca