Student Housing and Dining (SHD): Staging Area / Formwork Fabrication

Middle Section - Parking Lot 5

Commencing on Monday February 1, the western portion of the middle section of Parking Lot 5, south of the drive lane will be fenced off to enable formwork fabrication and delivery staging for Building Two of the SHD project. (See map attached).

Access will be maintained for vehicles using the roadway at the south of the parking lot, including the entrance to South Tower loading dock.

From time to time during this period, the formwork will be shipped to site via Gate Three, at the south-east of the construction site. Traffic control personnel will be in place for all formwork moves.

Monday, February 1, 2021 to Friday, July 30, 2021

View / Download Facilities Notice - SHD Staging Area / Formwork Fabrication

Primary Contact/ Organizer name: David Hill, Senior Project Manager
Primary Contact/ Organizer email: david.hill@collierprojectleaders.com

Secondary Contact/ Organizer name: Gerry Underhill, Project Manager
Secondary Contact/ Organizer email: gunderhill@uvic.ca