Student Housing and Dining: Site Preparation Work – Construction Activities W/C Sept. 16

Site Preparation Construction Zone

For the week commencing Monday September 16, Facilities Management and the Construction Managers, EDK, will be undertaking the work noted below.

Service Road
Work will continue at the Sinclair Road entrance. Grading will be completed and asphalt will be laid. This will necessitate road closures. A separate notice will be issued confirming the dates and times of any road closures.

Mailboxes
Work will commence to relocate some of the temporary mailboxes and continue all week.

Masonry
Installation of brickwork to be completed at Joseph Cunliffe.

Electrical
A small fenced area will be set up south of the SUB on Monday and Tuesday to pull in new electrical feeds.

September 16 – September 20;  7:30am to 4:00pm

View/ Download Facilities Notice - SHD Site Prep Constr Activities Sep 16

Primary Contact/ Organizer name: David Hill, Senior Project Manager