Student Housing and Dining: Site Preparation Work – Construction Activities W/C Jun 17

Site Preparation Construction Zone

In the week commencing Monday June 17, Facilities Management and the Construction Managers, EDK, will be undertaking the work below.

Deconstruction 
Commons north bridge deconstruction continues. Work will be limited on Wednesday June 19 for existing conference bookings.

SUB / GSS Service Road 
Concrete work commences on streetlight bases and conduit trenching.

New SUB Masonry Wall 
Excavation continues, when complete the footings will be poured.

Hydro Duct Bank 
Trenching continues to the east and south of the SUB ending near Ring Road.  The concrete pour to form the duct-bank commences on Wednesday.

Site Boundary 
Due to the hydro duct trenching, the pathway from the SUB  toward Cadboro Commons will be closed. All other site fencing remains in place.

June 17 – June 21, 2019 – 7:30am to 4:00pm

View/ Download Facilities Notice - SHD Site Prep Work-Constr Activities

Primary Contact/ Organizer name: David Hill, Senior Project Manager
Primary Contact/ Organizer email: david.hill@colliersprojectleaders.com

Secondary Contact/ Organizer name: Scott Kingham, Project Manager
Secondary Contact/ Organizer email: skingham@uvic.ca