General Access,  Stairs and Landing Installations
Monday: Commons North second floor access to grade reinstated.
Monday: At grade access at North end of Commons reinstated.
Monday: Access at West side of Commons closed for two weeks.
Thursday – Friday: Temporary access stairs to West side Craigdarroch.
Friday: Temporary landing at ramp to Emily Carr and Margaret Newton.

Demolition of Commons West Bridge
Wednesday – Friday: Demolition of the West bridge from Commons.

New SUB Back of House Area
Monday – Wednesday: Generator pad preparation/pour.

Service Road Improvements
Tuesday – Wednesday: Curb prep and partial installation - NOTE: Access Road may be blocked periodically.
Tuesday – Friday: Stump grinding south of Joseph Cunliffe.

Sidewalks
All week: Preparation for concrete walkways.

July 22 – July 26, 2019 – 7:30am to 4:00pm

View/ Download Facilities Notice - SHD Site Prep Weekly Constr Activities-July 22

Primary Contact/ Organizer name: David Hill, Senior Project Manager
Primary Contact/ Organizer email: david.hill@colliersprojectleaders.com

Secondary Contact/ Organizer name: Scott Kingham, Project Manager
Secondary Contact/ Organizer email: skingham@uvic.ca