Student Housing and Dining: Site Preparation Work – Construction Activities W/C Aug 19

Site Preparation Construction Zone

In the week commencing Monday August 19, Facilities Management and the Construction Managers, EDK, will be undertaking the work below.

General Access and COM Area Deconstruction
Building envelope repairs at Craigdarroch and Commons (all week)Install temporary stairs west of Cadboro Commons (Mon – Tues)

Craigdarroch Area
Trailer removal from parking lot 5 (Mon – Tues)
Clean up and landscaping by trailer location parking lot 5 (Wed – Fri)
Install mailboxes in temporary location (all week)

Service Road and SUB Area
Switchover to new SUB Genset (Tues: 4:30 – 7:30 pm)
Sidewalk installation north of Service Road (Tues –Fri)
Sidewalk installation south of Joseph Cunliffe (Wed – Fri)
Concrete slab infill east side of SUB (Tues – Wed)
Road curb installation (Wed – Fri) - tentative
Connect catch basin behind SUB building (TBD)
Irrigation and tree planting (all week)

August 19 – August 23, 2019 – 7:30am to 4:00pm

View/ Download Facilities Notice - SHD Site Prep Weekly Constr Activities-Aug19

Primary Contact/ Organizer name: David Hill, Senior Project Manager
Primary Contact/ Organizer email: david.hill@colliersprojectleaders.com

Secondary Contact/ Organizer name: Scott Kingham, Project Manager
Secondary Contact/ Organizer email: skingham@uvic.ca