Student Housing and Dining – Building One Tower Crane Removal

SHD Construction Site

Between Friday, September 17 and Sunday, September 19, Ellis Don Kinetic will be dismantling and removing the tower crane from Building One of the SHD project.

At noon on Friday September 17, a large mobile crane will arrive on site through Gate 1 (see sketch attached). Crews will then dismantle the crane in stages, and these will be removed by trucks using the same access route. During the operation trucks may be parked in the lay-by between the SUB and the GSS, but the service road will remain open at all times.

Work is expected to be completed on Saturday, September 18; however, Sunday, September 19 is being held as a reserve day. 

Friday, September 17 – Sunday, September 19, 2021

View/ Download Facilities Notice - SHD Bldg One Tower Crane Removal

Primary Contact/ Organizer name: David Hill, Senior Project Manager
Primary Contact/ Organizer email:  david.hill@colliersprojectleaders.com

Secondary Contact/ Organizer name: Colin Merriam, Project Manager
Secondary Contact/ Organizer email: colinmerriam@uvic.ca