Petch Level 2 - BCMB BSL2 Lab Upgrade - Renovation Work Over UVic Holiday Break
Petch Level 2 - Rooms 246 and 242
Facilities Management is working with Aral Construction Ltd. to undertake renovations to upgrade PCH 246 to BSL2 research lab.
Completion of epoxy resin flooring installation has been scheduled as part of the renovation in Rooms 246 and 242. Odour mitigation controls will be in place.
Data piping installation has been scheduled in 246, 249, 299f and in the Level 2 corridor.
FMGT apologizes for any inconvenience this work may cause.
Monday, December 27, 2021, 7:00am to 5:00pm - Flooring work in 246 and 242 (accessed through 239)
Wednesday, December 29, 2021 to Friday, December 31, 2021, 7:00am to 5:00pm – Conduit installation work in 246, 249, 299f and Level 2 corridor
View/ Download Facilities Notice - Petch Level 2 Reno - Holiday Schedule
Contact/ Organizer Name: Kim Frechette, Project Manager
Contact/ Organizer Email Address: kfrechette@uvic.ca