David Turpin Building B150-B165 ENVI Renovation
DTB B150-B165
Facilities Management will be working with Aral Construction (2014) Ltd. and their subcontractors to renovate interior spaces in DTB B150-B165.
Concrete trenching and coring work has been scheduled for Thursday, August 19, 2021 from 4:00 pm – 8:00 pm.
There will be increased noise levels and some building vibration during this work. We apologize for any inconvenience this may cause.
Project Schedule: July 22 – November 19, 2021
Trenching and Coring Work: August 19, 2021 4:00 pm – 8:00 pm
View/ Download Facilities Notice - DTB B150-B165 ENVI Reno-Coring
Contact/ Organizer Name: Linda Boggs, Project Manager
Contact/ Organizer Email Address: lboggs@uvic.ca